X
    Categories: News

Casey documents suggest at-grade bias

The state Casey Arborway team has released documents that suggest the state was biased in favor of an at-grade street network plan before the public process even started, though it still allowed for the possibility of a bridge replacement.

Early internal meeting notes mention an “Eisenhower Concept” and an “Olmsted Concept,” presumably referring to a new bridge and an at-grade street network. The design team decided to focus on developing the “Olmsted Concept.”

Emails, meeting notes and other internal documents pertaining to the Casey project before community involvement began were finally released to Design Advisory Group (DAG) and Bridging Forest Hills member Kevin Moloney late last month following a Freedom of Information Act (FOIA) request, after nine months of delay.

Bridging Forest Hills is a pro-bridge group that is pushing for the Casey project to be reset in favor of a new bridge instead of the chosen at-grade design.

Though Moloney told the Gazette that some requested documents still have not been released, he said that the documents that have been released “shout the message” that the state Department of Transportation (MassDOT), the agency in charge of the project, was biased in favor of an at-grade surface street network from the beginning.

“I think [whole process] was a ruse,” Moloney told the Gazette last week. “I think it was a phony deal right from the beginning.”

Gazette emails to MassDOT asking for comment and clarification were not returned by press time.

The first Working Advisory Group (WAG) meeting, the precursor to the DAG, was held in March 2011, following at least four months of internal meetings.

On Jan. 24, 2011, a meeting of project consultant firm HNTB employees and City and MassDOT officials met to discuss what to say about the Casey project at its first public meting. Notes from that meeting say, “a viaduct [replacement bridge] solution must clearly be an alternative. The process will determine the solution.”

But those notes also state that the focus should be on at-grade alternatives and that a bridge alternative would be available if at-grade was infeasible. They also state that talk of a replacement bridge should be kept generalized and should not mention a specific two-lane bridge design at all.

“If at the end of the study, we cannot come to a collective decision for an at-grade solution then we can proceed with a viaduct design,” the notes state. “We should focus on finding at-grade solutions. However, we may be pushed in that direction [of a bridge] as the study advances.”

A Jan. 21, 2011 email from then-MassDOT head Jeffrey Mullan to other MassDOT officials states that, “…this is a legacy issue. We can make it just like Olmsted planned it in 1878.”

Frederick Law Olmsted designed the Emerald Necklace system of parks in Boston in the 1870s and 1880s, including the Arborway in JP.

Notes from a Nov. 2, 2010 meeting between HNTB, MassDOT and other consultants, mention two concepts being developed: an “Eisenhower Concept” and an “Olmsted Concept.” Neither concept is explained in any of the documents the Gazette received.

However, Dwight Eisenhower was president of the U.S. from 1953 to 1961 and is remembered for launching the interstate highway system.

The Nov. 2 meeting notes state that, “the direction was given to base the alternatives on the Olmsted Concept.” Those notes also state, “an overpass may not be off the table for an alternative.”

Relocation for the 39 bus is also mentioned in conjunction with expanding capacity to service that bus in those same notes. The relocation of the 39 bus within Forest Hills station was not brought up to the DAG until late last year.

Notes from a Dec. 21, 2010 meeting between HNTB and City and MassDOT officials state that the “anticipated budget” for the project was $28 million, while noting that the projected cost for rebuilding the overpass would be $70 million to $80 million.

Notes from that same meeting also state that the group discussed identifying three at-grade alternatives and agreed that a bridge option should not be taken off the table.

Those same notes identify the need for a community-based working group. The City stated the importance of calling it an “Advisory Group, so the role was clear.”

The first WAG meeting, held on March 16, 2011, was not intended to be public. The Gazette reported at the time that it appeared that MassDOT was more enthusiastic about a surface road option, while residents were more interested in a new bridge. The meeting was essentially private and its attendees were not representative of the public at large.

State Rep. Liz Malia said at the time that she believed MassDOT has a “bias” toward the surface road option.

Meeting minutes from that March 16, 2011 WAG meeting confirm that then-City liaison John Romano told the group, “We are here because there are no preordained solutions.”

“There’s all this circumstantial evidence to suggest at-grade was [the state’s] first choice from beginning. It all points very clearly at what their intention was,” he told the Gazette last week. “I don’t think they ever gave a [replacement] bridge alternative a fair shake.”

Moloney first filed requests for the behind-the-scenes documents, which include emails, traffic analyses, cost estimates and other data pertaining to the Casey Arborway, in June 2012. By law, government agencies have 10 days to respond to such requests.

Following a December 2012 letter from the state Supervisor of Public Records that said MassDOT had “failed to meet its burden” and it needed to either release the documents or provide a breakdown of costs to release them, Moloney wrote MassDOT a check for $518.74 to cover some of those costs.

The check was received by MassDOT on Feb. 6 but was not cashed until March 12, after the Gazette started reporting for this article.

MassDOT released some documents to Moloney March 13, believing it had fulfilled all his requests, including two that incurred no charge, MassDOT spokesperson Michael Verseckes told the Gazette at the time.

“We sent him what we had,” he said.

Moloney told the Gazette that he has yet to receive all the items he requested and has paid for. These include more emails and meeting notes. They include notes from a meeting between Mayor Thomas Menino and Mullan, which was mentioned in some of the released documents.

“It defies common sense that MassDOT does not have in its possession, custody or control the public records” Moloney has requested, he writes in a March 21 letter to MassDOT, a copy of which Moloney provided to the Gazette.

Moloney first appealed to the Public Records Division of the Secretary of the Commonwealth’s office last August and then again in September. Public Records does not have the power to enforce its determinations.

Updated version: This version clarifies that the first meeting of the Casey Overpass replacement process was essentially private and its commentary non-representative of public opinion.

Rebeca Oliveira: Reporter at the Jamaica Plain and Mission Hill Gazettes.

View Comments (3)

  • The Pro-bridge discussion is a stunning example of our unwillingness to accept change and our difficulty accepting someone else's vision or decision. There should be no surprise that professional transportation planners and administrators developed thoughts on best outcomes early on in considering the condition of the Casey Overpass. The Gazette story, which itself is bias toward controversy and feeding Mr. Maloney conspiracy suspicions, could have been written to illustrate how despite the obvious, MassDOT gave the bridging approach serious consideration.

  • The Casey Overpass was constructed in the early 1950s to span two elevated train lines and a trolley turnaround that no longer exist. They are not coming back thanks to the sunken lines of the Southwest Corridor. As a neighbor, a close observer of the process for many months as well as a student of the evolution of the designs for this project to date, it has always seemed to me that the professionals involved - with the help and oversight of volunteers representing the interests of the community at large and their common goals - have been seeking the best 21st century transportation solution for the entire area. They are attemoting to rationalize the traffic patterns in a complicated transit hub that has evolved piecemeal for more than two centuries. The solutions evolving now will and should involve changing traffic patterns on the ground throughout the project area. The goal is not an idyllic restoration of 19th century parkway notions, but certainly the history of the area can and should inform all decisions about what works, what doesn't, what's necessary, what isn't, what the result should look like and how it should be used? I firmly believe that the majority of the community has confidence in the professionals, and supports their efforts going forward (not backwards). I hope for a day when we can put the bickering (and the lopsided Gazette coverage) behind us and celebrate the opening of the new Casey Arborway sometime in late 2016.

    • No, the overpass was not constructed to span two train lines. The overpass was built to get the Morton street/Arborway traffic out of the Washington/South street traffic. The spanning of the tracks was a by-product of the need to solve the traffic problem that had built up at that intersection. Returning the Overpass traffic to the ground is going to return the same problem the Overpass was built to solve. Stopping Arborway traffic at Washington street is going to add to pollution in the district, as vehicles have to stop and go in both directions. It is also going to slow bus traffic from Forest Hills station north.

      Olmsted's Arborway was designed to allow the 1% from the Back Bay to take Sunday drives out of the city in their expensive carriages. There will be no 'returning' to the Olmsted plan - only a 21st century aping of it. Forest Hills is not a park - it is a transportation hub. Trying to return to an era that didn't last ten years makes no sense. The railroad tracks - which preceded the Arborway - were raised on a bridge just about the same time the Arborway was built, and the Elevated line was built within ten years. Essentially, there never was an Olmsted's Arborway that can be returned to.

Related Post